Turnaround
Adriatic Vela 42
Awaiting review · owner Luka Perić · target launch 14:30
Demo data
BlockedPreparing for departure
Open high incident: Starboard topsides scrape, fender-pile contact while berthing. Approx. 1.2 m through gelcoat into the laminate, 60-80 cm above the waterline between stanchion 3 and the midship cleat. No cracking in the laminate and no water in the bilge. Photographed at 09:05; the scrape sits under the guard-wire base plate, so this hull does not move until a workshop signs it off.
12/13 required checks complete
Arrival & handover
Return condition review
Completed · Luka Perić
Keys/documents reconciliation
Completed · Luka Perić
Clean & prepare
Interior clean
Completed · Ana Jurić
Linens/reset
Completed · Ana Jurić
Deck rinse
Completed · Ana Jurić
Fuel & water
Fuel level/log
Completed · Toni Marin
Fresh water
Completed · Toni Marin
Waste check
Completed · Toni Marin
Inventory & safety
Galley inventory
Completed · Ana Jurić
Lifejackets/fire safety count
Completed · Ivo Radić
Technical
Engine visual check
Completed · Toni Marin
Systems test
Completed · Toni Marin
Technical inspection
To do · unassigned
Crew & launch
Skipper brief
To do · unassigned
Launch review
To do · unassigned
Report incident
Launch review
Readiness is not departure approval. Required checks and open safety incidents must be cleared before a launch-ready decision.
12/13 required checks satisfied · 1 open incidents